I. CHAIRPERSON TO CALL MEETING TO ORDER II. CHAIRPERSON TO CALL ROLL III. CITIZEN COMMENT
Approval of the minutes for the meeting held on September 18, 2017.
Discussion with possible action to utilize $31,632.85 originally obligated by the MPO for PS&E of the Loop 20 Extension from US 59 to the Jacaman Overpass to be used for the preliminary engineering for identifying drainage ponds along Loop 20. (CBI Funds- FY 2018 Letting).
Discussion with possible action to place digital signage on FM 1472 (Mines Road) intended to notify the driving public of congestion. 1. Report by TxDOT on possible sign locations, cost estimates, and funding sources for digital signage on Mines Road.
Report by TxDOT on "wish list"/recommendations from the Texas Transportation Institute (TTI) Mines Road Study pertaining to proposed City of Laredo facility improvements that would improve the function of Mines Road.
Discussion with possible action on the $2.4 million, Proposition I, Category 2 funds allocated to project CSJ 0086-14-077, intended to provide for construction of an interchange at the international airport, with an estimated construction cost of $14,785,990. Latest estimated letting date is fiscal year (FY) 2024.
Discussion with possible action on Hachar Road.
Administrative change to the TIP Amendment approved October 16, 2016 meeting approving PS&E funds for Jacaman and Airport Overpasses. Remove Airpo1t overpass and replace with Del Mar overpass utilizing the existing allocated funds. (CBI funds -FY2018 Letting)
Status of submission of Infra Grant application.
Presentation by TxDOT on the IH 35 Corridor Projects from mile marker 6 to mile marker 30.
TxDOT report on the feasibility of implementing a bike lane on FM 3338.
TxDOT report on the status of ongoing construction projects.
Status report on the Regional Mobility Authority (RMA).
Letting date for Flecha Lane/Las Cruces realignment project CSJ 0922-33-076 is proposed to be moved from September 2017 (FY 2018) to August 2018 (FY 2018).
G. Letting date for Calton Railroad grade separation project (CSJ 0922-33-093) is proposed to move from November 2017 (FY 2018) to August 2018 (FY 2018). VI. ADJOURNMENT
I. CHAIRPERSON TO CALL MEETING TO ORDER II. CHAIRPERSON TO CALL ROLL III. CITIZEN COMMENT
Approval of the minutes for the meeting held on September 18, 2017.
Discussion with possible action to utilize $31,632.85 originally obligated by the MPO for PS&E of the Loop 20 Extension from US 59 to the Jacaman Overpass to be used for the preliminary engineering for identifying drainage ponds along Loop 20. (CBI Funds- FY 2018 Letting).
Discussion with possible action to place digital signage on FM 1472 (Mines Road) intended to notify the driving public of congestion. 1. Report by TxDOT on possible sign locations, cost estimates, and funding sources for digital signage on Mines Road.
Report by TxDOT on "wish list"/recommendations from the Texas Transportation Institute (TTI) Mines Road Study pertaining to proposed City of Laredo facility improvements that would improve the function of Mines Road.
Discussion with possible action on the $2.4 million, Proposition I, Category 2 funds allocated to project CSJ 0086-14-077, intended to provide for construction of an interchange at the international airport, with an estimated construction cost of $14,785,990. Latest estimated letting date is fiscal year (FY) 2024.
Discussion with possible action on Hachar Road.
Administrative change to the TIP Amendment approved October 16, 2016 meeting approving PS&E funds for Jacaman and Airport Overpasses. Remove Airpo1t overpass and replace with Del Mar overpass utilizing the existing allocated funds. (CBI funds -FY2018 Letting)
Status of submission of Infra Grant application.
Presentation by TxDOT on the IH 35 Corridor Projects from mile marker 6 to mile marker 30.
TxDOT report on the feasibility of implementing a bike lane on FM 3338.
TxDOT report on the status of ongoing construction projects.
Status report on the Regional Mobility Authority (RMA).
Letting date for Flecha Lane/Las Cruces realignment project CSJ 0922-33-076 is proposed to be moved from September 2017 (FY 2018) to August 2018 (FY 2018).
G. Letting date for Calton Railroad grade separation project (CSJ 0922-33-093) is proposed to move from November 2017 (FY 2018) to August 2018 (FY 2018). VI. ADJOURNMENT