I. CHAIRPERSON TO CALL MEETING TO ORDER II. CHAIRPERSON TO CALL ROLL III. CITIZEN COMMENT
Approval of the minutes for the meeting held on February 20, 2018.
Motion to authorize a 2018 Call For Projects for the Laredo MPO Transportation Alternatives (TA) Set-Aside Program, in order to allocate $344,000 in TA federal funds, requiring a 20% match of $86,000, totaling $430,000 in total project costs.
Discussion with possible action for authorizing the WCCL RMA to move forward with the North Laredo/ Webb County Transportation Planning Study as presented on 11/20/17 before the Laredo MPO Policy Committee with the understanding that the Laredo MPO will reimburse the WCCL RMA for up to 80% of the cost of the study at a later date with funds from the remaining 2015 Coordinated Border Infrastructure program. The remaining 20% will be provided by the WCCL RMA as the local match. The cost of the study is estimated at $635,000.
Discussion and possible action on a set-back development policy on Loop 20, Mines Road and other major arterials.
Discussion with possible action on Hachar-Reuthinger Road.
Status report on the River Bank Road Project.
B. Status report on the Regional Mobility Authority (RMA). VI. ADJOURNMENT
I. CHAIRPERSON TO CALL MEETING TO ORDER II. CHAIRPERSON TO CALL ROLL III. CITIZEN COMMENT
Approval of the minutes for the meeting held on February 20, 2018.
Motion to authorize a 2018 Call For Projects for the Laredo MPO Transportation Alternatives (TA) Set-Aside Program, in order to allocate $344,000 in TA federal funds, requiring a 20% match of $86,000, totaling $430,000 in total project costs.
Discussion with possible action for authorizing the WCCL RMA to move forward with the North Laredo/ Webb County Transportation Planning Study as presented on 11/20/17 before the Laredo MPO Policy Committee with the understanding that the Laredo MPO will reimburse the WCCL RMA for up to 80% of the cost of the study at a later date with funds from the remaining 2015 Coordinated Border Infrastructure program. The remaining 20% will be provided by the WCCL RMA as the local match. The cost of the study is estimated at $635,000.
Discussion and possible action on a set-back development policy on Loop 20, Mines Road and other major arterials.
Discussion with possible action on Hachar-Reuthinger Road.
Status report on the River Bank Road Project.
B. Status report on the Regional Mobility Authority (RMA). VI. ADJOURNMENT